CILA, SCIA or planning permission in Sicily: which one you need

Before renovating a bathroom, opening a window or extending a house, the question is always the same: which permit is required? The answer varies from region to region, and Sicily has its own rules. Anyone relying on a national guide risks submitting the wrong application.

In this article, we explain when a CILA or SCIA is sufficient, when planning permission is required, and when no authorisation is needed. These are the general rules: the specific circumstances must always be checked for the property in question.

In brief: which permit for which works

PermitWhen neededAn example
NoneRoutine maintenance and works specified by lawRefurbish the interior finishes
CILAMajor maintenance not involving structural elements; internal worksMoving an internal wall
SCIAWork on structural elements or façades, and anything not covered by the other listsCutting an opening in a load-bearing wall
Planning permissionNew-build projects, urban regeneration, major refurbishmentsBuilding a house or extending it

Why the rules are different in Sicily

Throughout Italy, the building industry is governed by the Consolidated Building Act, Presidential Decree No. 380/2001. In Sicily, this also applies, but with the exceptions set out in Regional Law 16 of 2016, which was largely rewritten by Regional Law 23 of 2021 and amended by Regional Law 2 of 2022 and Regional Law 27 of 2024.

The most significant difference concerns what is not included in the lists. At national level, a project not included in the lists falls under the CILA. In Sicily, it falls under the SCIA: the regional law stipulates that projects not covered by the lists set out in Articles 3 and 5 must be notified via a certified notification.

When no permit is required

Article 3(1) lists the building works that require no permit at all. The main ones are:

  • routine maintenance;
  • the removal of architectural barriers, provided this does not involve the installation of external lifts or structures that alter the building’s outline;
  • heat pumps with a nominal useful heat output of less than 12 kW;
  • pergolas, retractable awnings and gazebos that can be easily removed, for use with legally compliant properties;
  • the removable panoramic windows and awnings, including pergola-style ones, added in 2024.

Permit-free does not mean rule-free. Town planning regulations, anti-seismic standards, health and safety regulations, and the Code of Cultural Heritage and Landscape must still be complied with.

This is why even permit-free works may require authorisation. If the property is subject to a restriction of which the owner is unaware – such as a landscape restriction – a pergola or an awning may require landscape authorisation. If carried out without authorisation, it is not always possible to regularise the situation afterwards: Article 167 of the Code permits an assessment of landscape compatibility only in limited cases, and excludes works that create usable floor area or volume. It is advisable to check before starting: if you have any doubts, please contact us.

When a CILA is sufficient

The CILA, a certified notification of commencement of works, is the procedure for internal refurbishment. Article 3(2) includes, amongst other things:

  • extraordinary maintenance that does not involve structural elements, including the opening of internal doors, the relocation of internal walls, and the division or amalgamation of units with the same intended use;
  • internal alterations which do not alter the building’s external dimensions, intended use or number of units, do not increase the usable floor area, do not affect the facades facing public roads or squares, and do not compromise the structural integrity;
  • new technical installations serving existing buildings, together with the associated plant rooms, within the limits laid down by law;
  • the installation of thermal insulation on the building envelope of existing buildings.

A qualified professional is required to sign off on the design documentation and certify, on their own responsibility, that the works comply with regulations and that the structural elements are not affected. The notification must also specify the contractor. If the notification is not filed, the fine is 1,000 euros, reduced by two-thirds if the notification is submitted voluntarily whilst the works are in progress.

When is a SCIA required?

The distinction between this and the CILA often comes down to a single word: structural. Article 10 requires a SCIA, a certified notification of commencement of activity, for:

  • extraordinary maintenance, restoration and conservation work relating to structural elements or façades;
  • changes to façades facing public roads or squares, where these do not form part of a refurbishment requiring planning permission;
  • amendments to planning permission that do not affect town planning parameters or building volumes, or that do not constitute a substantial change;
  • prefabricated private swimming pools installed in-ground within the limits laid down by law;
  • all compliant works that do not appear on the lists for minor building works, CILA and planning permission.

Under the standard SCIA procedure, work may commence from the date of submission, as provided for in Article 19 of Law 241 of 1990. The local authority carries out checks afterwards, and if the requirements are not met, it may prohibit the work from continuing. For this reason, the application must be checked for accuracy before it is submitted.

When is planning permission required?

Article 5 stipulates that planning permission is required for works that transform the land through urban development or building:

  • new construction;
  • urban regeneration;
  • building renovation which results in a structure that is wholly or partly different and alters the overall volume;
  • in Zone A, that is historic centres, the same renovation when it changes the intended use;
  • in the case of properties protected under the Code of Cultural Heritage and the Landscape, works that alter the building’s outline, overall volume or façades;
  • the conversion of attics, outbuildings, ancillary rooms, cellars and basements for residential use.

The Consolidated Act allows sixty days for the preliminary investigation and a further thirty days for the decision. The time limit may be interrupted once to request additional information and is doubled for particularly complex projects. If the deadline expires without a reasoned refusal, tacit consent is deemed to have been granted, although different rules apply where the property is subject to planning restrictions. These are statutory time limits: the actual time taken depends on the relevant authorities and any other necessary approvals.

The SCIA as an alternative to planning permission

Certain works requiring planning permission may be carried out by submitting an alternative SCIA: specific building renovations, works governed by implementation plans with precise planning and volumetric provisions, the conversion of existing volumes for residential use, and the completion of unfinished works. In such cases, the notification must be submitted at least thirty days before the actual start of the works.

In Zone A and on listed buildings, renovation may proceed in this way only if three conditions are met: the floor structure already exists, notification of the works in accordance with Article 93 of the Consolidated Law, and an energy classification compliant with the decree of 26 June 2015. The reverse also applies: those eligible to use the standard SCIA procedure may always apply for planning permission without paying the building contribution.

How to submit an application in Noto, and how much does it cost?

In Noto, CILA, SCIA and planning permission applications are submitted online via the municipality’s one-stop building office (SUE) portal. You log in using SPID or the credentials issued by the municipality, select the type of application and attach the relevant documents and declarations. The application is usually submitted by the appointed professional. The status of the application can be tracked via the same platform, and notifications are sent to your digital address.

Each application pays a processing fee, paid to the Municipal Treasurer. The amounts are set out in Municipal Executive Resolution No. 169 of 26 November 2024:

ApplicationProcessing fee
CILA200 euros
SCIA300 euros
SCIA as an alternative to planning permission400 euros
Planning permission for up to 1,000 m³600 euros
Planning permission for over 1,000 m³800 euros
Amendment to the planning permission500 euros
Certified notice of fitness for use (SCA)250 euros per dwelling

A 16-euro revenue stamp is normally required with the application. These are municipal fees only: they do not include the building contribution, which is payable for the planning permission and the alternative SCIA, opinions from other bodies such as the Superintendency, or the professional’s fee. The amounts shown are those in force as of November 2026: before paying them, it is advisable to check them with the municipality’s SUE.

Choosing the permit is not enough: restrictions and lawful status

Choosing the permit is only part of the job. First, there are two things that need to be checked.

Restrictions. A property in Zone A, subject to the Code of Cultural Heritage and Landscape, situated within parks and nature reserves or in areas subject to hydrogeological restrictions, may require an opinion or authorisation before work can begin. For SCIA notifications under paragraphs 1, 2 and 3 of Article 10, this is expressly stated in the law. In the historic centre of Noto, the provisions of the local development plan and the landscape plan also apply, and the process varies considerably from building to building.

Lawful status. A permit can only be filed for a property that is in order. Article 9-bis of the Consolidated Act sets out how this is demonstrated: by the permit that authorised its construction or governed the most recent works on the whole property, supplemented by later permits. For buildings constructed at a time when no permit was required, the original land registry details or other supporting documents apply. Any discrepancy discovered once the application process has begun may alter the project and the timetable.

In summary

To get a clear picture, three questions are enough: do the works affect the structure or the façades? Do they alter the volume, shape or intended use? Is the property in Zone A or subject to planning restrictions? The permit depends on the answers, but the final decision rests with a qualified professional who has inspected the building and its documentation.

If you are considering a project in Noto or the Val di Noto, you can find out how we work and the answers to frequently asked questions on the page about our architectural services in Noto. The regulations referred to are those in force as of November 2026.

ParliamoneApri il modulo

    Let us talk

    A couple of lines about the project you have in mind are enough to start.




    I reply within two working days.